Special Services Building Improvements

 

The improvements of the Special Services Building to house the Turner County Middle School began in January of 2014


February 5, 2016

The process began with the pressure washing of the exterior of the building.

 

 

 

 

February 8, 2016- Cleanup work begins to get the building ready for the improvements.

 

 

 

 

 

 

 

 

 

 

February 9, 2016

 

 

 

 

 

 

 

February 10, 2017

 

 

 

 

   

 

February 13, 2017

 

  

 

 

  

 

  

 

February 14, 2017

     

 

 

 

   


February 16, 2017

      

 

   

 

 

February 18, 2017

 

 

  

 

February 22nd, 2017

         

 February 23rd, 2017

  

   

 February 24th, 2017

  

 

 February 25th, 2017

 February 27th, 2017

  

 

February 27th, 2017 Floors being sanded

 

March 1st , 2017

March 2nd , 2017

March 3rd, 2017

March 4th, 2017

March 6th, 2017

  

  

  

  

March 7th, 2017

  

  

March 13th, 2017 - Door Replacement Begins

  

  

  

  

March 14th, 2017

  

 

March 15th, 2017

 

March 16th, 2017

  

   

 

March 17th, 2017

  

April 3rd, 2017

  

  

  

  

 

April 6th, 2017 Special Services Gym Improvements Begin

  

  

  

  

 

April 10th , 2017 Window Installation Begins

April 25th, 2017 Improvements continue

 

 

 

April 26th, 2017 Replacement of Water Fountain & Plumbing

 

 

April 27th, 2016 Awning work begins

 

 

May 11th Concrete Improvements Continue at Special Services Gym

 

Pressure Washing Begins at Special Services

 

May 11th Additional restroom improvements continue

 

May 11th Additional Wiring

 

May 11th Ceiling Tiles Replacement

 

May 12th, 2017

 

 

May 15th, 2017 Pressure Washing

 

Concrete

 

 

May 16th, 2017

 

May 17th, 2017

Pressure Washing

 

Ceiling Tile Replacement

Windows Arrive

 

 

Painting

 

Additional Concrete

 May 18th, 2017 Getting ready for the move

Before

  

  

  

May 18th, 2017 6th Grade Academy Improvements Start

Before

 

  

 

 May 23rd, 2017 Playground equipment begins to be moved to elementary school

 

May 23th, 2017 Work Continues

 

 

 

 

 

May 24th, 2017 Fence Moving Begins

Painting Continues

Tile Work Moving Forward 

 

 

May 26th, 2017 The "Move" Goes Into Full Swing

Floor Waxing

 

Moving Pre-K 5-26-2017

  

  

  

 

June 1st, 2017

  

  

Playground Move Continues

 

June 4th, 6th Grade Academy Improvements Begin

  

  

June 8th, 2017 - Painting at the 6th grade academy gets underway

  

  

June 9th, 2017 - Commode Replacement at 6th Grade Academy

Before                                                                                     After

 

June 9th, 2017 - Playground move continues

  

June 10th, 2017 - Windows Installment Begins

 

 

 

June 13th, 2017

Light Fixtures changed out

Playground Continues to be moved

 

June 14, 2017 - Windows continue to be installed

 

 

June 15th, 2017 Work Continues

  

  

June 19th, 2017

 

 

 

 

June 19th, 2017 Continued

June 20th, 2017

 

 

 

June 22nd, 2017